Three days is very long or three days very short?
time:2018-04-29 13:39  

  Three days, very long?

  People in the industry know that for a power plant auxiliary boiler with more than 4000 parts and more than 300 control points, it is too short to check and debug within 3 days. Challenging this seemingly impossible task, RUNPAQ did it.

  In Datang Gongyi power plant, RUNPAQ refreshes the commissioning time of auxiliary boiler of power station. The electrical engineer completed the commissioning of the auxiliary boiler of the power plant in only three days, four days ahead of the planned seven days, and the ignition was successful.
   
    Furnace ignition in Datang Gongyi project:

Ignition instruction from man-machine interface
Bright flame confession in the furnace: I do not speak, I am only responsible for perfect combustion.

The rapid improvement of the debugging speed of the monomer comes from the company's familiarity with the custom requirements of the power plant boiler. The RUNPAQ electrical engineer has a good technical function. After repeated debugging code sentences and simplified instructions, the debugging time of the monomer is shortened. Once again, the task is done efficiently and splendidly. It is a successful capture of the owner's heart and a full sense of trust.

Boot program optimization

After the ignition is successful, the RUNPAQ boiler enters the drying oven stage, and the follow-up work is steadily advancing. RUNPAQ's electrical engineer, carrying his bags, rushed to the next scene, and the boiler room behind him was fading away.